CASE STUDY:
Western Turner Syncline
Electrical, communications and fire installations to various facilities.
Client & Department | Georgiou |
Location | Rio Tinto Western Turner Syncline |
Project No. & Name | Western Turner Syncline Stage 2 |
Value | 7.6 Million |
Date | June 2022 |
Project Duration | 14 Months |
Installations to Tyre Change Workshop, LME Workshop, HME Workshop and Administration, Ice Room and Medical buildings.
Project Key deliverables included:
-
Installation of new 33KV HV underground supply and new Transformer.
-
Electrical, Communications and Fire Installation to Tyre Change Workshop and ancillary building.
-
Electrical, Communications and Fire Installation to LME Workshop
-
Electrical, Communications and Fire Installation to HME Workshop. 4 bay Extension
-
Electrical, Communications and Fire Installation to Administration, Ice Room and Medical buildings
-
Installation of Site Wide Area Lighting. 10M & 20M light towers.
-
Electrical and communications Installation of MEM dome shelter
-
Electrical Installation of Site Access Boom Gates including solar hybrid power supply.
-
Electrical Installation of water Infrastructure.
-
Installation of Fibre Optic site wide reticulation
- Significant increase of scope from IFT – IFC
- Accelerated electrical construction schedule with multiple open work fronts.
- Day shift / Night shift operations to allow access while working around other trades.
- Market skilled labour shortage
- COVID impacted resource manning levels and availability
- Successful completion and handover of stage 2, Ability to coordinate and manage all scope deliverables as well as those of our business partners under our contractor quilt.
- Extensive knowledge of the Rio Tinto systems and procedures.
- Incident and injury free operations