CASE STUDY

Wi-Fi Uplift Projects

Rio Tinto had been experiencing poor Wi-Fi performance across multiple NPI facilities, warehouses and workshops. This project was initiated to upgrade the network infrastructure as part of a broader program to modernise operations and improve workforce connectivity.

WSE HP BannerStrip scaled
Client & Department Rio Tinto IS&T
Location Paraburdoo, Tom Price, Marandoo, Rail (2/6/7/8 Mile, Emu Ops, Rosella, Ti Tree)
Project Name Wi-Fi Uplift Projects
Value 2.9 Million
Date October 2024
Project Duration 12 Months

The scope involved the installation and commissioning of Cisco Wireless Access Points in areas identified during site surveys as having poor or no coverage. The outcome was a significant uplift in network performance, delivering fast, reliable Wi-Fi to support voice, video and data applications.

  • Installation of 648 Cisco Wireless Access Points across 10 sites.
  • Installation of 25,000+ metres of communications cabling and containment.
  • Communications commissioning.
  • Installation of 648 Cisco Wireless Access Points across 10 sites.
  • Installation of 25,000+ metres of communications cabling and containment.
  •  Communications commissioning.
  • Extensive knowledge of Rio Tinto systems, standards and procedures.
  • Innovative, solution-focused approach to overcoming project challenges.
  • Proven technical expertise and quality workmanship.
  • Strong leadership and a collaborative, safety-first culture.
  • Project team members received Rockstar Awards from the Network Connectivity Team and Mobility Programme for outstanding collaboration, safety and coordination.