CASE STUDY

Western Turner Syncline

Electrical, communications and fire installations to various facilities.

WSE HP BannerStrip scaled
Client & Department Georgiou
Location Rio Tinto Western Turner Syncline
Project Name Western Turner Syncline Stage 22
Value 7.6 Million
Date June 2022
Project Duration 14 Months

Installations to Tyre Change Workshop, LME Workshop, HME Workshop and Administration, Ice Room and Medical buildings.

  • Installation of new 33KV HV underground supply and new Transformer.
  • Electrical, Communications and Fire Installation to Tyre Change Workshop and ancillary building.
  • Electrical, Communications and Fire Installation to LME Workshop
  • Electrical, Communications and Fire Installation to HME Workshop. 4 bay Extension
  • Electrical, Communications and Fire Installation to Administration, Ice Room and Medical buildings
  • Installation of Site Wide Area Lighting. 10M & 20M light towers
  • Electrical and communications Installation of MEM dome shelter
  • Electrical Installation of Site Access Boom Gates including solar hybrid power supply
  • Electrical Installation of water Infrastructure.
  • Installation of Fibre Optic site wide reticulation
  • Significant increase of scope from IFT – IFC
  • Accelerated electrical construction schedule with multiple open work fronts.
  • Day shift / Night shift operations to allow access while working around other trades.
  • Market skilled labour shortage
  • COVID impacted resource manning levels and availability
  • Successful completion and handover of stage 2
  • Ability to coordinate and manage all scope deliverables as well as those of our business partners under our contractor quilt.
  • Extensive knowledge of the Rio Tinto systems and procedures.
  • Incident and injury free operations