CASE STUDY
West Angelas Lube Chillers
Installing new Lube Chillers to keep up with expected operational tonnage.


Client & Department | RTIO Projects |
Location | West Angelas Mine site |
Project Name | Lube Chillers |
Value | 150K |
Date | 2020 |
Project Duration | 4 days |
The West Angelas process plant Lube Chillers were not keeping up with the required operational tonnage that was expected from the plant with the demand being greater than the original design. In addition to this the original equipment had become dated and was in need of repairs.
Project key deliverables
- De-commission of existing Lube Chiller skids in a planned Shut down
- Installation of Generator Power Supplies to keep Critical Equipment online whilst the plant was Shut down
- Installation of new Lube Chiller Skids and Chiller rooms
- Power and Control Cabling install to relevant marshalling panels, motors, heaters and instrumentation
- Design and Installation of Cabling Systems to RTIO Specification which could withstand the harsh environment of being situated at the Primary Crusher
- Installation of New Feeder Modules
- Electrical Commissioning of the Project
Key Challenges
- Completing the Project inside of a limited Shut Down period
- Working along side various contractors in a confined area
- Over coming wiring issues with existing cabling changes not documented in both the substation and marshalling panels
The Weststate Advantage
- Over coming challenges that arise with a new installation on a fixed plant asset with no time extensions possible.
- Extensive knowledge of the RTIO systems and procedures
- A well developed culture among workers who have extensive experience in the mining industry
- Provide a complete turn key package from start to finish
- Provide the client with options to move forward when challenges arise
Other info
- ILTI Free Project
- Positive client feedback with great understanding how complex the task was in the given time for completion.